The work on University Avenue West includes replacement of sanitary sewer, storm sewer and upsizing the watermain. Improvements to sidewalks and drainage including the addition of sidewalk from College Avenue to Caledonia Street. This project will improve the quality of water and sewer systems for residents in the area, now and into the future.

Timeline

  • 2024-2025: Detailed design
  • Fall 2024: Geotechnical work begins
  • Summer 2025: Utility relocation
  • February 2026: Tender
  • April 2026: Construction

Map of construction area

Construction limits: College Avenue West and University Avenue West to Gordon Street

Community engagement

We commit to communicating with businesses and residents about this project. The City will host an open house event in Fall 2024 to provide project information. Details of the event and materials will be posted online when available.