About the project
The City is improving Silvercreek Parkway North between Woodlawn Road and Speedvale Avenue West.
We are upgrading existing watermain and sanitary sewers, installing new curbs, adding multi-use paths and repaving the road.
Upgrading the watermain and sanitary sewers ensures we can support our community as the population grows.
The multi-use paths will improve active transportation connectivity in Guelph, allowing cyclists to safely travel from the Silvercreek bike lanes immediately south of Speedvale Avenue West to the Woodlawn multi-use path system.
In addition, we are upgrading the three bus stops along this stretch of road from grade-level shoulder stops to raised concrete pads for improved accessibility and comfort.
Latest updates
-
Silvercreek Parkway North full closure starting August 30
August 16, 2024 -
Silvercreek Parkway North lane reductions starting July 22
July 15, 2024
Questions and comments
We are committed to communicating with businesses and residents about this project, and we encourage you to visit haveyoursay.guelph.ca/silvercreek-parkway-north to post questions and comments at anytime. Our project team will respond to ensure you get the information you need.
Construction timeline
Construction will be completed in two phases:
Phase 1: Woodlawn Road to Campbell Road – Summer 2023
Phase 2: Campbell Road to Speedvale Avenue – Spring 2024
Map of the construction area
For more information
Anindita Datta, Project Manager
Engineering and Transportation Services
City of Guelph
519-822-1260 Extension 2756