Notice date: April 30, 2024
About the project
The City is working with TM3 Inc. to install a new pedestrian crossover on the North leg of Downey Road and Pheasant Run Drive /Quail Creek Drive.
Work begins May 20
Work is expected to begin on or about Monday, May 20, and will take about two weeks to complete, weather permitting.
Lane reductions and delays expected
The City will ensure that two-way traffic is maintained at all times and directed by a traffic control officer. Drivers should follow the detour signage posted. While a full road closure is not planned, delays are expected.
Pedestrian access
The sidewalks in this area will remain open and accessible during construction.
Property and business access
All businesses in the construction area will remain open and accessible throughout construction.
The City will maintain access to driveways in the construction area during working hours (7 a.m.–7p.m.) The contractor will ensure an alternative access is provided in these scenarios.
Map of construction area
The City appreciates your patience, understanding and co-operation during this important construction project. Updates will be posted on guelph.ca/construction.
For more information
Shaymaa Al-ani, Traffic Signal Technologist II
Transportation Engineering, Engineering and Transportation Services
City of Guelph
519-822-1260 extension 2041
[email protected]