About this project
We’re transforming a former municipal parking lot into a compact district nestled in Guelph’s historic core that will create a renewed area of activity, commerce and civic space for the local community and city.
The Baker District redevelopment project is a multi-year, multi-faceted project that will include a new library, parking garage and public squares in the Downtown core along Baker Street, Chapel and Park Lanes. The project phasing includes developing the site from the current status of a surface parking lot, through site preparation activities which include archaeological clearance, then construction of private development towers including commercial and residential spaces, along with the new parking garage, library and public squares.
Check out the progress so far!
As a landmark city-building initiative, the Baker District redevelopment further revitalizes our downtown and—by extension—improves our entire city’s economic and social prosperity.
This means:
- more people living downtown and contributing to the City’s tax base to fund municipal programs and services
- more jobs due to an increase in demand for retail and commercial services
- an increase in retail spending for current and new businesses
- more people visiting and learning downtown; contributing to a vibrant and healthy downtown.
The project also contributes to Guelph’s growth target: a population of 203,000 people and an employment base of 116,000 jobs by 2051. The City’s Official Plan earmarks Guelph’s downtown to achieve a density target of 150 people and jobs combined per hectare by 2031, and to be a focus for high density employment, residential development, public infrastructure and services, and multimodal transportation.
The Baker District redevelopment project is being developed as a One Planet Living community. One Planet Living is a planning and sustainability framework based on a desire to reduce the impact of the way we live, build, and consume. The Central Library and parking garage will also support the City’s Race To Zero goals, and becoming net carbon neutral by 2050, by meeting the Canadian Green Building Council Net Zero Carbon Design standard.
The new central library is the first stand-alone library in Canada to achieve Canada Green Building Council®‘s Zero Carbon Building – Design Standard™ certification.

Guelph Public Library entrance, artist rendering. Subject to change.
Timelines
- Project Design and Tender Documents Q2 2021 to Q4 2022
- Tender and Award Q1 to Q2 2023
- Construction and building commissioning Q3 2023 to 2026
- Operational startup of library and parkade end of 2026.
Project status and last quarter update
Central Library project status
Within scope
On schedule
Within budget
Baker Parkade project status
Within scope
On schedule
Within budget
Public squares project status
Within scope
On schedule
Within budget
- Building Structural Concrete works continued through Q1 and be generally finished in Q2, 2025.
- The building’s concrete structure will continue to be poured through the first half of 2025.
- Build envelope works are expected to start in Q2, 2025, along with interior works for the Library.
- Lane closures can be expected later on in 2025 as building envelope and masonry works progress.
- Right of Way Works along Baker Street are expected to be completed in 2025.
- Construction is expected to be completed on the Parkade and the Library at the end of 2026.
- The City received the first payment from the GICB grant for works completed on the library of over $ 4 million dollars to help with the costs for the construction of this facility.
Latest updates
-
Speed River Trail – closure of user-created paths
April 30, 2025 -
Announcing Guelph’s 2025 Artists-in-Residence
April 29, 2025 -
Water barrier install for downtown patios starting May 3
April 29, 2025 -
625 Hanlon Road closed starting May 12
April 29, 2025 -
Delhi Street lane shifts starting May 8
April 29, 2025
Community engagement
Get involved! Stay informed! Have your say! Sign up at haveyoursay.guelph.ca to receive information about engagement opportunities. You can also review information about engagement we’ve done in the past.
Resources
- Guelph Public Library
- Baker District Redevelopment Urban Design Master Plan, May 2021
- Baker District archaeological, environmental and geotechnical investigations
- Downtown Secondary Plan
- Downtown Community Improvement Plan
Additional project details
- Executive sponsor: Jayne Holmes, Deputy Chief Administrative Officer Infrastructure, Development and Environment
- Project manager: Stephen Gazzola, Project Manager, Facility Design and Construction
- Approved budget: Central Library: $62,070,000; Baker Parkade: $15,900,000; public squares: $2,600,000
- Funding sources: Central Library: 21 per cent grant, 26 per cent development charges, 53 per cent tax; Baker Parkade: 100 per cent rate; public squares: 100 per cent development charges
- Target completion: Q4 2026
For more information
Stephen Gazzola, Project Manager
Facilities and Energy Management
City of Guelph
519-822-1260 extension 3886