Health indicators provide a visual representation of the status of a project in respect to the project baseline or plan being tracked. At a quick glance, the health indicator can let you know if a project is on track or at risk. The health indicators are applied to scope, schedule, and cost baselines.
Pictogram |
Description |
Within scope
On schedule
Within budget
|
- Scope: Project is progressing to deliver approved original scope.
- Schedule: Project is progressing according to the approved original schedule.
- Budget: Cost spending is progressing according to the approved original budget and plan.
|
Under review
Under review
Under review
|
- Project on hold. Provide notes explaining reasons.
|
Risk of not meeting scope
Risk of not meeting schedule
Risk of exceeding budget
|
- Scope: Status is deviated from the approved scope and requires revisions to meet original deliverables.
- Schedule: Status is deviated from the approved schedule within amber tolerance as identified in the Project Management Plan (PMP).
- Budget: Status is deviated from the approved budget within amber tolerance of estimated budget as identified in the PMP.
|
Not meeting scope
Behind schedule
Over budget
|
- Scope: Status is significantly deviated from the approved scope. Initial scope is unlikely achieved, requiring Steering Committee support or approval to revise the plan.
- Schedule: Status is significantly deviated from the approved schedule. Initial schedule is unlikely achieved, requiring Steering Committee support or approval to revise the plan.
- Budget: Status is significantly deviated from the approved original budget. Delivery within approved budget is unlikely achieved, requiring Steering Committee support or approval to revise the plan.
|
Within revised scope
On revised schedule
Within revised budget
|
For cases when baseline revisions are a result of scope changes.
- Scope: Project is progressing to deliver approved revised scope.
- Schedule: Project is progressing according to the approved revised schedule.
- Budget: Cost spending is progressing according to the approved revised budget and plan.
|
Within revised scope
On revised schedule
Within revised budget
|
- For cases when baseline revisions are a result of project implementation challenges.
- Scope: Project is progressing to deliver approved revised scope.
- Schedule: Project is progressing according to the approved revised schedule.
- Budget: Cost spending is progressing according to the approved revised budget and plan.
|
Risk of not meeting revised scope
Risk of not meeting revised schedule
Risk of exceeding revised budget
|
- Scope: Status is deviated from the approved scope and requires revisions to meet revised deliverables.
- Schedule: Status is deviated from the approved revised schedule within amber tolerance as identified in the PMP.
- Budget: Status is deviated from the approved revised budget within amber tolerance as identified in the PMP.
|
Not meeting revised scope
Behind revised schedule
Over revised budget
|
- Scope: Status is significantly deviated from the approved revised scope. Revised scope is unlikely achieved, requiring Steering Committee support or approval to further revise the plan.
- Schedule: Status is significantly deviated from the approved revised schedule. Revised schedule is unlikely achieved, requiring Steering Committee support or approval to further revise the plan.
- Budget: Status is significantly deviated from the approved revised budget. Delivery within approved budget is unlikely achieved, requiring Steering Committee support or approval to further revise the plan.
|