Historic Coal Gasification Plant Site Investigation

The Fountain Street parking lot was the site of a coal gasification plant from 1871-1957.

The City is taking a proactive approach to investigating impacts of the former coal gasification plant both on-site and in the surrounding area. Once investigation work is complete the City will determine what steps may be required for the site and surrounding area.

Off-site investigation work includes testing on streets and properties that surround the parking lot including Fountain Street, Wyndham Street and Surrey Street.

Monitoring of the Speed River, storm sewer outfalls and groundwater has also been done in connection with the investigation.

The City expects to complete its environmental investigation in 2028. Reports will be made available as they are completed.

Timeline

  • 1988: Guelph Gas Works study
  • 1990: Initial environmental assessment
  • 1990: Bedrock groundwater monitoring installations
  • 1996: Remediation work plan
  • 1998: Site file review (of previous reports)
  • 2004: Physical surveys of households and businesses south of the site
  • 2014: On-site investigation (Phase one and phase two environmental site assessments)
  • 2015: Surrey Street geotechnical investigation
  • 2015: Surrey Street environmental investigation
  • 2016: Fountain Street and Wyndham Street environmental investigation
  • 2016: Soil vapour testing along Surrey Street
  • 2016: Environmental inspection, monitoring and sampling of the Speed River and storm sewer outfalls
  • 2018: Vertical and horizontal delineation, evaluation of subsurface utilities, upstream Speed River sampling
  • 2020: Additional Investigation of buried utilities, additional horizontal delineation, well decommissioning and repairs
  • 2024: Characterize non-aqueous phase liquid, assess natural attenuation, determine hydraulic conductivity in hydrogeologic units at the Site
  • 2026-2027: Complete multi-phase extraction investigation, expanded soil vapour monitoring, and enhanced natural attenuation assessment