Notice date: August 28, 2026
What’s happening:
We’re paving the following streets: Carrington Drive, from south of Lovett Lane to Ryder Avenue, Ryder Avenue from Carrington Drive to Lovett Lane; and Lovett Lane from Ryder Avenue to Ryder Avenue. The City of Guelph’s contractor, Brantco Construction, will complete this work. It includes repairing concrete curbs, adjusting stormgrates, manhole covers and valves; and paving the road surface.
Why:
This project is part of the City’s Annual Paving Program. Find more information about this program at guelph.ca/living/construction-projects/annual-paving/.
When:
We anticipate starting work on or about August 31, and expect it to take between four to six weeks to complete, weather permitting. Updates about this project can be found on guelph.ca/construction.
Changes during construction:
Traffic lanes: Lane reductions throughout the construction area. Please follow all posted signs and any flag people directing traffic for safety.
Sidewalks: There may be temporary impacts to sidewalks during construction.
Guelph Transit: No changes. Visit guelph.ca/transit for details.
Waste collection: No changes.
Property access: There may be temporary impacts to driveways and laneways during construction. Every effort will be made to maintain access during working hours (7 a.m. to 7 p.m.).
On-street Parking: There may be temporary impacts to on-street parking (where permitted) during curb repairs and paving.
Please use alternative parking on nearby streets.
Please be advised that the City or its paving contractor, Brantco Construction, will not approach you to re-pave your driveway. Third-party contractors are not permitted to operate in active City construction zones. In some instances, due to the removal and replacement of curb along driveway aprons, the City may need to re-pave a section of the bottom of a private driveway. If required, paving costs would be covered by the City.
Map of construction area

Thank you for your patience during this construction project.
For more information
For more information about the project, or if you require this document to be provided in an alternative format as per the Accessibility for Ontarians with Disabilities Act (2005), please contact: