Notice Date: November 20, 2026
What’s happening:
Demikon Construction Ltd. is carrying out dewatering activities, installing sanitary sewer infrastructure, and repaving the road. The City is supporting this work by closing the road during construction.
Why:
This project supports the development at 121 Hanlon Creek Boulevard. For more information about the development, please contact [email protected].
When:
Work is expected to begin on or about November 23 and will take approximately three weeks to complete, weather permitting.
Changes during construction:
Traffic lanes: Hanlon Creek Boulevard will be closed to through traffic for the duration of the project. Local traffic will continue to have access along Hanlon Creek Boulevard; however, there will be no through access at 121 Hanlon Creek Boulevard.
The signed detour route will be Laird Road to Gordon Street to County Road 34 to County Road 35 and returning to Laird Road.
Guelph Transit: Guelph Transit Route 19 will be temporarily detoured during construction. Visit guelphtransit.ca for information regarding stop changes and route detours.
Waste collection: No changes.
Map of construction area

For more information
For more information about the project, or if you require this document to be provided in an alternative format as per the Accessibility for Ontarians with Disabilities Act (2005), please contact [email protected] or visit guelph.ca/construction