Guelph Central Station

About this project

The Guelph Central Station will be fully accessible to serve public transit riders and the business needs of Guelph Transit. The building will meet the City’s sustainability and energy goals and improve access to multi-model transportation. The proposed two storey building will include: an accessible public waiting area, accessible public washrooms, ticket area, passenger information, driver rest area and staff work areas.

Timelines

  • Detailed design procurement: Q2 to Q3 2023
  • Detailed design and approvals: Q4 2023 to Q4 2025
  • Tender ready in 2026

Project status and last quarter update

Within scope

On schedule

Within budget

  • The City and consultant and currently undertaking the detailed design process and will continue through the detailed design process through 2024.
  • The City completed the initial site plan review meeting in Q1 2024.
  • Permitting and site plan works will continue in parallel with the detailed design through the remainder of 2024.

Additional project details

  • Executive sponsors: Colleen Clack-Bush, Deputy Chief Administrative Officer, Public Services and Jayne Holmes, Deputy Chief Administrative Officer, Infrastructure, Development and Enterprise Services
  • Project manager: Amir Bhatti, Project Manager, Facility Design and Construction
  • Approved budget: $1,265,000 (planning and design phase only)
  • Funding sources: 100 per cent tax reserves
  • Target completion: Tender ready in 2026.

For more information

Ian Scott
Manager, Facility Design and Construction
519-822-1260 extension 3496
[email protected]