Guelph police headquarters: October 2019 construction update

The renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in October 2019.

Progress to date

East wing

  • East wing is now open to the public
  • Landscaping is complete
  • Major deficiencies are complete

West wing

  • Exterior brickwork is 98 per cent complete
  • Painting, flooring and finishes are 90 per cent complete
  • Exterior siding is 90 per cent complete
  • Epoxy in garage floors are complete

Looking ahead to November 

East wing

  • Review and complete any deficiencies

West wing

  • Achieve partial occupancy of the west wing
  • Complete linear works on the west side
  • Complete siding work
  • Carry out work on available areas of the existing building