The renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in September 2019.
Progress to date
East wing
- Landscape is complete
- Major deficiencies are complete
West wing
- Exterior brickwork is 90 per cent complete
- Painting, flooring and finishes are 85 per cent complete
- Exterior siding is 90 per cent complete
- Epoxying the garage floors is complete
Looking ahead to October
East wing
- Review and complete any deficiencies
West wing
- Complete flooring, painting and carry on with finishings
- Achieve partial occupancy
- Complete landscaping
- Complete siding work