Guelph police headquarters: September 2019 construction update

The renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in September 2019.

Progress to date

East wing

  • Landscape is complete
  • Major deficiencies are complete

West wing

  • Exterior brickwork is 90 per cent complete
  • Painting, flooring and finishes are 85 per cent complete
  • Exterior siding is 90 per cent complete
  • Epoxying the garage floors is complete

Looking ahead to October

East wing

  • Review and complete any deficiencies

West wing

  • Complete flooring, painting and carry on with finishings
  • Achieve partial occupancy
  • Complete landscaping
  • Complete siding work