Construction notice: Eramosa Road lane reductions starting September 23

At Glenhill Place

About the project

The City is working to reconstruct Glenhill Place from Eramosa Road to the end of the cul-de-sac. Work includes pouring sidewalk, curb works and paving on Eramosa Road.

Work is being completed by Morely’s Contracting.

Work starts September 23

Work is expected to start on or about September 23, and take about two weeks to complete, weather permitting.

Lane reductions expected

Eramosa Road will undergo lane reductions during the project. Two way traffic will be maintained at all times. Please follow posted signs for safety. A full road closure is not expected, however, delays should be expected.

Pedestrian access

The south sidewalk on Eramosa Road will be closed during construction. Please use nearby crossings to use the north sidewalk.

Property and business access and parking

All businesses in the construction area remain open and accessible throughout construction.

Every effort will be made to maintain access to driveways in the construction area during working hours (7 a.m.–7 p.m.). Construction activities and equipment movement may temporarily impact access to private property.

Map of construction area

The City appreciates your patience, understanding and co-operation during this important construction project. Any updates will be posted on guelph.ca/construction

For more information

Steven Di Pietro, P. Eng, Project Engineer
Engineering and Transportation Services