The renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in August 2019.
Progress to date
East wing
- East wing is now open to the public
- Landscape is completed
- Major deficiencies are completed
West wing
- Exterior brickwork is 90 per cent complete
- Painting, flooring and finishes are 70 per cent complete
- Exterior siding is 85 per cent complete
Looking ahead to September
East wing
- Review and complete any deficiencies
West wing
- Complete flooring and painting, carry on with finishing
- Achieve partial occupancy
- Epoxy garage floors
- Complete landscaping work
- Complete siding work