The renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in July 2019.
Progress to date
East wing
- East wing is now open to the public
- Exterior finishes are complete
- Landscaping is complete
West wing
- Exterior brickwork 90 per cent complete
- Painting, flooring and finishes are 70 per cent complete
- Exterior siding is 90 per cent complete
- Exterior sidewalk work in progress
Looking ahead to August
East wing
- Review and complete any deficiencies
West wing
- Complete flooring and painting, carry on with finishing work
- Complete structural steelwork
- Complete siding work
- Complete epoxy floor coating of garage area