Guelph police headquarters: May 2019 construction update

The renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in May 2019.

Progress to date

East wing

  • East wing is now open to the public
  • Exterior finishes complete. The area is now being cleaned up for landscaping

West wing

  • Exterior brickwork 70 per cent complete
  • Painting, flooring and finishes 60 per cent complete
  • Exterior siding 80 per cent complete

Looking ahead to June

East wing

  • Start landscaping
  • Review and complete any deficiencies

West wing

  • Complete flooring and painting, carry on with finishing
  • Complete structural steelwork
  • Complete southwest brickwork
  • Complete demolishing additional areas in the existing building to facilitate renovation work
  • Complete siding work