Guelph police headquarters: March 2019 construction update

The renovation and expansion of Guelph Police Service’s headquarters are underway. Here is a summary of the work completed in March 2019.

Progress to date

East wing

  • East wing is now open to the public
  • Exterior finishes complete. The area is now being cleaned up for landscaping

West wing

  • Exterior brickwork 60 % complete
  • Painting, flooring and finishes have started
  • Mockup for holding cells complete. Work in remaining cells 95 per cent complete
  • Exterior siding moving along well

Looking ahead to April

East wing

  • Start landscaping
  • Review and complete any deficiencies

West wing

  • Complete drywall taping
  • Carry out painting and flooring work
  • Complete structural steelwork
  • Complete southwest brickwork
  • Complete demolishing additional areas in the existing building to facilitate renovation work
  • Carry out exterior blue skin and siding work