Guelph police headquarters: January 2019 construction update

The renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in January 2019.

Progress to date

East wing

  • Exterior finishes 98 per cent complete
  • Partial occupancy of east wing achieved

West wing

  • Exterior curtain wall glazing (non-structural outer covering of a building for weather protection) is 95 per cent complete
  • Third floor drywall boarding is 98 per cent complete and taping is 85 per cent complete
  • Mockup for holding cells complete, work in other cells 80 per cent complete
  • Southwest steel structure (building skeleton) is complete and masonry work is complete, roofing in progress

Looking ahead to February

East wing

  • Completion of exterior facade
  • Completion of public reception area
  • Review and complete any deficiencies before full occupancy

West wing

  • Completion of drywall taping
  • Completion of structural steel work
  • Completion of southwest roofing work
  • Complete drywall and taping in existing parts of the building
  • Commence flooring