Guelph police headquarters: December 2018 construction update

The renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in December 2018.

Progress to date

East wing

  • Exterior finishes 95 per cent complete
  • Partial occupancy of east wing achieved

West wing

  • Exterior curtain wall glazing (non-structural outer covering of a building for weather protection) is 90 per cent complete
  • Third floor drywall boarding is 95 per cent complete and taping is 25 per cent complete
  • Mockup for holding cells complete, work in other cells 75 per cent complete
  • Southwest steel structure (building skeleton) is complete and masonry work is about 65 per cent complete

Looking ahead to January

East wing

  • Completion of exterior facade
  • Review and address any deficiencies before full occupancy

West wing

  • Completion of drywall taping
  • Completion of structural steel work
  • Completion of southwest masonry work
  • Demolition of older parts of the building
  • Start renovations in existing parts of the building

guelph.ca/gpsreno