The renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in September 2018.
Progress to date
East wing
- Washroom fixtures are complete
- Wood door installation, including hardware, is complete
- Painting is complete
- Exterior wall finish (cladding) is 85 per cent complete
- Interior vinyl composite tile work is 95 per cent complete
- Inside woodwork is almost complete
- Paperwork for East wing partial occupancy is almost complete
West wing
- Exterior curtain wall glazing (non-structural outer covering of a building for weather protection) is 85 per cent complete
- Structural steel framing at the southwest corner, including deck, is complete
- Third floor drywall boarding is in progress
- New generators on firing range are in process of being connected
Looking ahead to October
East wing
- Partial occupancy
- Exterior facade completion
West wing
- Glazing for curtain wall complete
- Elevator doors installed
- Generator wiring and mechanical piping to be complete
- Drywall installation targeting 60 per cent completion