Guelph police headquarters: June 2018 construction update

The renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in June 2018.

Image shows construction progress in front lobby including partial sub floor, and completed walls and tiling

Front lobby progress photo June 2018

Progress to date

East wing

  • Ceramic flooring work complete
  • Ceiling complete
  • Men’s washroom and shower partition complete
  • Rooftop HVAC unit installed
  • Washroom fixtures 80 per cent complete
  • Wood door installation, including hardware, 80 per cent complete
  • Sheet vinyl flooring 75 per cent complete
  • Painting 60 per cent complete
  • Exterior wall finish (cladding) 60 per cent complete
  • Front entrance flooring poured and sidewalk complete

West wing

  • Roof on new addition complete
  • Exterior brickwork complete
  • Lower windows installed
  • Detention cell doors and frames installed
  • Generator frame complete and generator installed
  • Curtainwall frames (non-structural outer covering of a building for weather protection) 25 per cent complete

Looking ahead to July

East wing

  • Sheet vinyl flooring, carpet and painting will be completed
  • Fixed cabinets, countertops, shelves etc. will be installed
  • Washrooms fixtures (toilets, sinks, etc.) will be installed
  • Exterior wall finish (cladding and limestone) will be completed
  • Roof over existing wing will be completed

West wing

  • Steel framing installation continues on the east corner
  • Generators will wired to the building
  • Third and fourth floor curtainwall frame (non-structural outer covering of a building for weather protection) will be near completion
  • Detention cells painting will be about 50 per cent complete

guelph.ca/gpsreno