Guelph police headquarters: May 2018 construction update

The renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in May 2018.

Progress to date

West wing addition exterior block wall, May 2018

East wing

  • Ceramic floor finishes and wall tiling are 90 per cent complete
  • Lighting and ceiling in community room complete.
  • Existing stucco removed from about 30 per cent of the existing building
  • Steel frame for roof top unit is complete
  • Mill work is happening on site for built in cabinets, counter tops, shelves, etc.
  • Heating lines for the front entrance flooring installed

West wing

  • Finishes to existing roof complete
  • Membrane on new roof installed and sealed
  • South wall block exterior complete
  • West wall block exterior 75 per cent complete

Looking ahead to June

East wing

  • Sheet vinyl flooring installation will begin
  • Fixed cabinets, countertops, shelves etc. will be installed
  • Washrooms fixtures (toilets, sinks, etc.) will be installed
  • Front entrance flooring will be poured

West wing

  • New roof to be completed
  • Steel framing to continue on the east corner and curtainwall (non-structural outer covering of a building for weather protection)
  • Exterior brickwork will be near completion