The three-year renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in February 2018.

Interior picture of construction of the community room in the police headquarters building. It shows plywood and drywall on the walls as well as some resting against the wall, ready to be used. The image is filled with natural light, coming in through large windows. Other construction and building materials appear, such as steel beams and plumbing material ready to be installed.

The future Community room at the Police Headquarters building.

Progress to date

East wing addition

  • Aluminum caps on glass frames are installed
  • Drywall framing/board and taping is almost complete
  • Roof above firing range almost complete
  • Paint and wall finish is 20 per cent complete
  • Ceramic floor tile installation is 20 per cent complete
  • Started installation on mechanical and electrical fixtures, and trims

West wing addition

  • Third and fourth floor framing for curtainwall (non-structural outer covering of a building for weather protection) is 30 per cent complete
  • Detention cell is nearly complete

Looking ahead to March

East wing addition

  • Final installation of the roof top HVAC unit
  • Continue finishes on walls and floors
  • Install doors and hardware
  • Install new generators

West wing addition

  • Install last section of new detention cells
  • Start southwest steel framing
  • Start roofing membrane
  • Continue curtainwall (non-structural outer covering of a building for weather protection) framing