The three-year renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in December 2017.

Scaffolding goes up for work to finish the exterior of the southwest corner of the west addition.
Progress to date
West wing addition
- Remaining floor in existing garage removed
- Last section of concrete slab poured in the garage
- Interior blockwork 90% complete
- Mezzanine mechanical and electrical 70% complete
- Steel support for roof parapet started
- Third storey enclosed for heating and finishes
- Office design mock-ups 50% complete
- Stone roof ballast removed from existing west roof
East wing addition
- Drywall installation underway
- 90 per cent of roof sealed
- Public washroom blocked in and plumbing is roughed in
- Glazing for glass curtainwall 90 per cent complete
- Electrical and mechanical rough-ins underway
- Exterior blockwork on second level is finished
- Structure for new generator above firing range is complete with concrete deck and slab poured
Looking ahead
West wing addition
- Finish roofing over firing range and existing west roof
- Exterior architectural block to start
- Finish pouring slab on grade for detention cell
East wing addition
- Finish roofing
- Glazing for glass curtainwall
- Installation of interior drywall, taping to start
- Mechanical ducting and electrical rough-ins continue
- Concrete topping poured for plaza entrance