Guelph police headquarters: November 2017 construction update

The three year renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in November 2017.

Image shows construction progress on west wing

Block exterior back-up wall of the west wing addition along Farquhar Street

Progress to date

West wing addition

  • Elevator installation 50% complete
  • Exterior and interior block walls 90% complete
  • Third floor stud framing and door frame installation 80% complete
  • Third and fourth floor mechanical and electrical 50% complete
  • Steel framing and deck installed for new generators
  • Last storm sewer connection done
  • Staircase extension complete with roof deck

East wing addition

  • Aluminum window frames installed
  • Roofing 50% complete
  • Concrete slab for front plaza entrance poured

Looking ahead

West wing addition

  • Exterior finish block install to begin
  • Slab poured for new generator
  • Steel framing at roof to begin for roof parapet

East wing addition

  • Finish roofing
  • Glazing for glass curtainwall
  • Installation of interior drywall

guelph.ca/gpsreno