The three year renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in November 2017.
Progress to date
West wing addition
- Elevator installation 50% complete
- Exterior and interior block walls 90% complete
- Third floor stud framing and door frame installation 80% complete
- Third and fourth floor mechanical and electrical 50% complete
- Steel framing and deck installed for new generators
- Last storm sewer connection done
- Staircase extension complete with roof deck
East wing addition
- Aluminum window frames installed
- Roofing 50% complete
- Concrete slab for front plaza entrance poured
Looking ahead
West wing addition
- Exterior finish block install to begin
- Slab poured for new generator
- Steel framing at roof to begin for roof parapet
East wing addition
- Finish roofing
- Glazing for glass curtainwall
- Installation of interior drywall