Guelph police headquarters: September 2017 construction update

The three year renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in September 2017.

Image shows the roof top construction on the west wing of the Guelph Police Headquarters

Fourth floor west wing roof formed and poured

Progress to date

West wing addition

  • Roof slab poured
  • Concrete slab flooring 60 per cent complete
  • Steel wall framing almost finished on third level administration space, mechanical and electrical installation underway
  • Fourth floor mechanical room wall installed
  • Southeast stairway foundation and second level walls poured
  • Southeast corner excavated and footings poured

East wing addition

  • Exterior stud wall and board installed on community room
  • Masonry walls of public washroom 75 per cent complete with mechanical and electrical rough-in
  • North east corner stairs poured. Opening for new exit created.
  • Underground site service installed

Looking ahead

West wing addition

  • Final concrete pour for elevator and staircase
  • Remove crane tower, infill openings
  • Finish concrete walls for stairs
  • Complete southeast corner foundation
  • Exterior masonry work to begin
  • Ongoing mechanical and electrical installation on third and fourth floors

East wing addition

  • Install aluminum framing for glass curtain wall of community room
  • Start roofing
  • Complete site services on southwest corner
  • Finish generator steel work

guelph.ca/gpsreno