The three year renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in August 2017.
Progress to date
West wing addition
- Finished pouring concrete slab for fourth floor
- Pouring concrete roof
- Preparing to pour concrete floor in parking garage
- Demolished existing stair and south wall next to Fountain Street entrance
- Installed new sprinkler room main
- Drywall framing for third floor offices underway
East wing addition
- Steel framework and roof deck complete
- Second level composite floor complete
- Site servicing and backfilling 50 per cent complete
Looking ahead
West wing addition
- Finish pouring concrete for roof and garage floor
- Complete tunnel foundation walls, columns and stair extension
- Finish steel framework around generator
- Install generator fuel tank
- Complete foundation wall and columns
- Complete all major formwork
- Finish steel installation over firing range
East wing addition
- Install roofing parapet and roof
- Finish site services