The three year renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in July 2017.
Progress to date
West wing addition
- Finished pouring concrete slab for third floor
- Pouring concrete slab for fourth floor
- Fourth floor roof deck forming underway
- Installing steel framing over the firing range for new generators
- Demolition of existing Fountain Street staircase to prepare for extension
East wing addition
- Concrete slab floors poured for men’s locker room and main floor entrance
- Sanitary street connection made
- Storm connection almost complete
Looking ahead
West wing addition
- Finish pouring concrete on fourth storey floor and roof deck
- Complete all major formwork
- Pour concrete in garage
- Finish steel installation over firing range
- Demolition of south facing staircase
East wing addition
- Installation of steel deck