Guelph police headquarters: July 2017 construction update

The three year renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work completed in July 2017.

Progress to date

West wing addition

  • Finished pouring concrete slab for third floor
  • Pouring concrete slab for fourth floor
  • Fourth floor roof deck forming underway
  • Installing steel framing over the firing range for new generators
  • Demolition of existing Fountain Street staircase to prepare for extension

East wing addition

  • Concrete slab floors poured for men’s locker room and main floor entrance
  • Sanitary street connection made
  • Storm connection almost complete

Looking ahead

West wing addition

  • Finish pouring concrete on fourth storey floor and roof deck
  • Complete all major formwork
  • Pour concrete in garage
  • Finish steel installation over firing range
  • Demolition of south facing staircase

East wing addition

  • Installation of steel deck