As of February 22, 2017, a summary of the work completed or underway.

New addition

  • Installed remaining curtain wall
  • Sprinkler mains in filtration room installed
  • Roof install underway including gutter tie in
  • Installing rails in elevator shaft and elevator machine room equipment
  • Continue spray foam install along exterior walls

Pool

  • Continue Myrtha gutter install, completed lap pool drain pipe install, started pool deck trench drain install, form surge tank lid
  • Ceramic floor tile work in change rooms
  • Locker install in pool change rooms
  • Continued backfilling of lap and teaching pools, excavated for pool deck drain piping
  • Continue installing pool underground pipe, start north gutter drain pipe install
  • Finish painting third floor walls, start painting natatorium high walls

Third floor

  • Continued painting third floor walls
  • Continue framing addition interior walls/bulkheads, continue framing third floor T-bar ceiling, start boarding addition interior walls
  • AV installation complete
  • Flooring in meeting room to be installed
  • Kitchenettes measured for install