Countdown is on!

With only 15 weeks left in the main construction schedule, there are many things happening at the Victoria Road Recreation Centre.

Behind the scenes

As of January 13, 2017, a summary of the work completed or underway.

Pool area

  • Teaching pool  has been poured
  • Main pool insert work has begun
  • Change rooms and washrooms are ready for plumbing fixtures and lighting
  • Open areas are awaiting glass glazing
  • Walls have been prepped for acoustic panels
  • Ceiling and duct work has been painted

New addition

  • Floor poured
  • Stair treads on all levels to be poured
  • Framing has begun for ne multipurpose room
  • Millwork measurements have been taken for customer service counter

Second floor

  • Masonry work continuing
  • Washroom upgrades underway
  • Railing installed
  • Lobby being prepared for concrete pour

Third floor

  • Viewing area glazing is installed
  • Painting to begin
  • AV screens installed in advance of drop ceiling installation
  • Site measurements have been for kitchenette areas in meeting rooms

Exterior

  • Penthouse work continues
  • Roofing of new addition continues
  • Courtyard structural steel in place

guelph.ca/vrrcrenovations