Construction continues on east and west wing additions

The three year renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work as of November 21, 2016.

What’s happening

  • Concrete foundation walls and columns/footings being poured
  • Waterproofing of foundation walls in east and west wings
  • Drywall installation in east and west wing additions
  • On-going mechanical and electrical rough-ins
  • Installation of hot water tanks
  • Energizing of electrical main switch gears and panels

Looking ahead

  • On-going foundation work on east and west wing additions
  • Complete installation of slab on grade of east wing
  • Erect steel structure for east wing addition
  • On-going mechanical and electrical rough-ins
  • Installation of catch basin and storm line
  • Removal of cooling tower
  • Intumescent painting of beams (for fireproofing)