Foundation work continues on east and west wings

The three year renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work as of October 27, 2016.

What’s happening

  • Backfilling of east wing addition foundation walls
  • Waterproofing of west wing addition foundation walls
  • West wing staircase wall and foundation
  • West wing corridor framed and boarded
  • Installation of heating lines, heat pump, boiler piping and venting, gas piping

Looking ahead

  • Backfill northeast side
  • Install elevator and staircase footing and foundation wall formwork, rebar, and concrete
  • Rough-ins for power, fire alarm panels, security system, and building automation system
  • Remove existing heaters and install new heaters
  • Masonry partitions to east and west side
  • Drywall boarding, insulation, and taping
  • Finish backfilling and waterproofing east wing addition
  • Install first level foundation walls and columns of west wing addition
  • Install slab on grade and underground services for west wing
  • Continue mechanical and electrical installation