The three year renovation and expansion of Guelph Police Service’s headquarters is underway. Here is a summary of the work as of September 30, 2016.
What’s happening
- 80% of the existing floor in the garage has been removed
- Backfilling of east wing foundation walls addition underway
- Installation of radon vertical stack at east wing
- Waterproofing of west wing addition foundation walls
- Installation of rebar in the staircase in the west wing shear wall is 80% complete
- Two columns in west staircase have been poured
- Information Technology (IT) closet framed and boarded on one side
- Third floor west wing corridor is 75% boarded
- West wing second floor west corridor has been framed and boarded
- Existing boiler lines removed from first and second floors, east side
- Penthouse boiler piping and venting being installed
- Hot water installed along with 50% of gas piping on the roof
Looking ahead
- Backfill north side of east addition
- Excavate for footings and walls along south side of east wing, install footings
- Install storm sewer to the east side
- Complete waterproofing to west wing lagging
- Complete bedrock removal
- Form and place rebar to west wing foundation walls
- Install new water main
- Continue installation of electrical conduits
- Install heating lines to first and second floors of west wing
- Install heat pumps on east side and hangers for heating lines
- Remove existing hot water tank