Recent Traffic and Construction Updates
Posted on Tuesday, May 15th, 2012
Road Closure Notice
Eramosa Road
Arthur Street N. to Delhi Street
Start: Thursday, May 24 07:00
End: Friday, May 25 17:00
Reason
Lead water service replacement.
Detour Route
Woolwich Street > Speedvale Avenue > Stevenson Street
Transit Impacts
Routes 12 & 13 will be affected.
Visit www.guelphtransit.ca for details on route changes.
Local/Emergency Access
No access through work zone.
For more information
Water Services
T 519-837-5627
E waterworks@guelph.ca
View the road construction and detour [...]
Posted on Friday, May 11th, 2012
CONSTRUCTION NOTICE
Speedvale Avenue
Stevenson Street to Waverley Drive
LANE REDUCTIONS START MAY 22
The reconstruction of Speedvale Avenue from Stevenson Street to Waverley Drive is scheduled to begin on Tuesday, May 22 and will be completed over two years. Two-way traffic will be maintained throughout construction, but motorists can expect delays.
ABOUT THE PROJECT
Stage 1 – May 22 to [...]
Posted on Monday, May 7th, 2012
Road Closure Notice
Laird Road
Hanlon Expy. (Hwy. 6) to Southgate Drive
Start: Wednesday, May 16
End: Fall 2013
Reason
Hanlon (Hwy. 6) / Laird Road interchange construction.
(Laird Road west of Hanlon (Hwy.6) scheduled for June 1.)
Detour
Hanlon Expressway / Clair Road / Southgate Drive
Local/Emergency Access
No access through work zone.
For more information
Fred Vock
Senior Contract Administrator, Morrison Hershfield
T 289-335-1167
E fvock@morrisonhershfield.com
Harv Anema
Office Administrator, Morrison [...]
Posted on Monday, May 7th, 2012
Construction open house
Clair Road Watermain
Clair tower booster station to Poppy Drive
The City of Guelph is hosting an open house to discuss the extension of the watermain from Clair tower booster station to the south end of Poppy Drive
Thursday, May 17
5-7 p.m.
South End Emergency Services Station
160 Clair Road West
Community Room
Why come to the open house?
You are [...]
Posted on Monday, May 7th, 2012
Construction Notice
Victoria Road South
Arkell Road to MacAlister Boulevard
Road closures May 14 to November
The City has hired Capital Paving Inc. to complete the reconstruction of Victoria Road South from Arkell Road to MacAlister Boulevard. Victoria Road South will be closed to through traffic during construction. Please follow posted detours on Arkell Road, Gordon Street and Stone [...]
Posted on Friday, May 4th, 2012
INFORMATION BULLETIN
Guelph crews put finishing toucheson downtown CN Rail bridge
One-day traffic disruption expected Sunday, May 6
GUELPH, ON, May 4, 2012 – The City is preparing to complete some finishing touches on the new CN railway bridge arching over Wyndham Street in downtown Guelph.
The work will require a one-day traffic interruption on Sunday, May 6 from [...]
Posted on Thursday, May 3rd, 2012
MTO continues local highway upgrades
GUELPH, ON, May 3, 2012 – This week, the Ministry of Transportation Ontario begins work on a new interchange at the intersection of the Hanlon Expressway (Provincial Highway 6) and Laird Road. Construction will continue until fall 2013.
Road closures and traffic interruptions
At times during construction the Hanlon Expressway will be reduced [...]
Posted on Thursday, May 3rd, 2012
CONSTRUCTION NOTICE
Gordon Street
Poppy Drive to Maltby Road
The City of Guelph has hired Cox Construction Inc. to remove and replace the asphalt surface, improve gravel shoulders and driveways, and mark bike lanes along Gordon Street from Poppy Drive to Maltby Road.
Traffic interruptions May 9-23
The road work will start on Wednesday, May 9 and is expected to [...]
Posted on Wednesday, May 2nd, 2012
CONSTRUCTION OPEN HOUSE
Clair Road Watermain
(Clair tower booster station to Poppy Drive)
The City of Guelph is hosting an open house to discuss the extension of the watermain from Clair tower booster station to the south end of Poppy Drive
Thursday, May 17
5-7 p.m.
South End Emergency Services Station
160 Clair Road West
Community Room
WHY COME TO THE OPEN HOUSE?
You are [...]
Posted on Tuesday, May 1st, 2012
The City will replace and or upgrade watermains, sewers, curbs, gutters, sidewalks, driveway aprons and the roadway along Woolwich Street between the Sleeman Centre and Macdonell Street, and along Macdonell Street to the East Parkade.
PARTIAL ROAD CLOSURES MAY TO JULY
Reconstruction is scheduled to start in May and take about 2 months to complete. Work is [...]