Stone Road East reconstruction Phase 1

Village Green Drive to Victoria Road South

The project

The project involves the reconstruction of Stone Road East between Village Green Drive and Victoria Road South including installation of storm sewer, curb and gutter, sidewalk and street lighting.  The reconstruction will widen Stone Road East to provide two vehicle lanes and one bicycle lane in each direction.

Construction timeline and traffic impacts

Reconstruction is expected to start on June 23, 2014 and take until late May 2015 to complete.  Reconstruction will be completed in stages to minimize impact on through traffic.  A two week closure to through traffic will be required at the start of the reconstruction.

Stone Road E Reconstruction

Latest updates

 
Anticipated staging, timing and impact on through traffic 
Stage Construction activity Anticipated timing Impact on through traffic
1 Culvert installation and storm sewer outlet Late June 2014 (approx. 2 weeks) Closed to through traffic
2 South side road widening and reconstruction Early July 2014 to late August 2014 One through lane open in each direction
3 North side road widening and reconstruction Late August 2014 to early October 2014 One through lane open in each direction
4 Utility relocation and street light installation Early October 2014 to late April 2015 Minimum one through lane open in each direction
5 Sidewalk installation and landscaping May 2015 Minimum one through lane open  in each direction

Traffic detour and property access

Through traffic will be detoured along Victoria Road South, Arkell Road and Gordon Street during the initial road closure.  Access to adjacent properties will be maintained as best as possible throughout the reconstruction.

Property inspections

OZA Inspections may contact you to arrange an interior/exterior inspection of any buildings on your property that are adjacent to the reconstruction area.  This inspection is a proactive measure intended to assess whether or not a property has any existing damage.  This information will be used to determine the contractor’s responsibility in the unlikely event of property damage during the reconstruction.

The City of Guelph appreciates your patience, understanding and co-operation during this important construction project.

For more information

Brad Hamilton
Project Engineer
Engineering Services
519-822-1260 extension 2319
brad.hamilton@guelph.ca
David Martinell
Construction Inspector
Engineering Services
519-222-5175
david.martinell@guelph.ca