Victoria Road South

This project is complete. Visit guelph.ca/construction to learn about current construction projects

The reconstruction of Victoria Road South from MacAlister Boulevard to Stone Road East is  anticipated to begin on or about Monday, June 24, 2013. The reconstruction will be undertaken by Cox Construction Limited from Guelph.

About the project

The project involves the reconstruction of Victoria Road between McAlister Boulevard and Stone Road East including installation of storm sewer, watermain, curb and gutter, sidewalk and street lighting. The reconstruction will widen Victoria Road South to provide two traffic lanes and one bicycle lane in each direction.

Victoria_Stone_Arkell_construction_map013

Updates

Latest updates

  No posts found, check back soon
 

Reconstruction, staging, detour and access

Reconstruction will be completed is stages to minimize impact on through traffic. A full closure will be required at the start of construction to install deep underground services. Anticipated staging, timing and impact on through traffic are detailed below.

Traffic will be detoured along Stone Road East, Gordon Street and Arkell Road during road and lane closures. Access to adjacent residential and commercial properties will be maintained throughout the reconstruction.

The City of Guelph appreciates your patience, understanding and co-operation during this important infrastructure renewal project.

Construction Schedule

STAGE

CONSTRUCTION ACTIVITY

EXPECTED TIMING

IMPACT ON THROUGH TRAFFIC

1

Deep underground service installation

June 24, 2013 for approx 2 Weeks

Closed to through traffic

2

West side widening and reconstruction

Early July 2013 to mid August 2013

One through traffic lane open in southbound direction

3

East side widening and reconstruction

Mid August 2013 to late September 2013

One through traffic lane open in each direction

4

Utility relocation and street light installation

Late September 2013 to December 2013

Minimum one through traffic lane open in each direction

5

Sidewalk installation and landscape restoration

Early May 2014 to early June 2014

Minimum one through traffic lane open in each direction open

For more information

Brad Hamilton, P. Eng., Project Engineer
Engineering Services
Planning, Building, Engineering and Environment
519-822-1260 extension 2319