East and west wing foundations almost done at Guelph police headquarters

West wing foundation walls and second floor slab at the Guelph police headquarters, a

West wing foundation walls and second floor slab at the Guelph police headquarters, as of January, 2017

The three year renovation and expansion of Guelph Police Service’s headquarters is underway. Here’s a summary of the work completed from November 2016 to January 2017.

Progress to date

  • East and west wing foundation work almost complete
  • Waterproofing of foundation walls
  • Drywall installation in east and west wing additions
  • Ongoing mechanical and electrical rough-ins
  • Energizing of electrical main switch gears and panels
  • Installation of hot water tanks
  • Cooling tower installed and covered-block

Looking ahead

  • Form second level of west wing
  • Erect east wing structural steel and deck
  • Continue mechanical and electrical installations
  • Construction of information technology rooms
  • Forming for parking garage

guelph.ca/gpsreno