Construction continues at Victoria Road Recreation Centre

Construction crews have been busy with the following aspects of the Victoria Road Recreation Centre renovation.

Behind the scenes

As of January 31, 2017, a summary of the work completed or underway.

New addition

  • Washroom  and waterline main rough-ins  going in
  • Masonry walls continue to be installed
  • Sprinkler pipe install
  • Third floor T-bar ceiling framing
  • Continue spray foam installation of addition exterior walls, fire spray underside of second/third floor mezzanines
  • Begin change room tile floor install
  • Curtain wall install
  • Door frame install continuing on all floors
  • Court yard base plates and steel installed
  • Metal roof install

Pool area

  • Underground pool deck drainage piping around pool
  • Continued addition duct install, insulate duct work in addition
  • Teaching pool ramp, bench, and steps formed and poured
  • Continuing Myrtha panel install
  • Lap pool drain pipe install
  • Natatorium acoustic panels painting
  • First floor ceiling taping in change rooms
  • Deck slab pour

guelph.ca/vrrcrenovations