East wing foundation almost finished at Guelph police headquarters

The three year renovation and expansion of the Guelph Police Service’s headquarters is underway. Here’s a summary of the construction work, as of December 12, 2016:

What’s happening

  • East wing foundation almost complete and west wing foundation expected to be 85% complete
  • Forming started  for parking garage
  • On-going mechanical and electrical rough-ins
  • Construction of IT rooms
  • Dog house demolition

Looking ahead

  • Complete west side footings and foundations
  • Form second level of west wing
  • East wing structural steel and deck
  • Generator structure to be built
  • Cooling tower installed and covered

guelph.ca/gpsreno