Partial occupancy of arena scheduled for October 1

Construction crews have been busy with the following aspects of the Victoria Road Recreation Centre renovation.

Behind the scenes

As of August 30, 2016, a summary of the work completed or underway.

  • Emergency lighting installed in arena
  • Footings poured in filtration room
  • Arena ceiling painted
  • Structural steel installed in penthouse
  • Ceramic tile installed in arena change room showers
  • Pool change room slab on grade poured
  • Watermain connection at Victoria Road
  • Partial occupancy of arena scheduled for October 1

For a behind-the-scenes look, visit guelph.ca/vrrcrenovations