Masonry work begins

Construction crews have been busy with the following aspects of the Victoria Road Recreation Centre renovation.

Behind the scenes

As of August 3, 2016, a summary of the work completed or underway.

  • Penthouse roof removed
  • New air handling roof top units installed
  • Structural steel in place for third floor barrier free area
  • West wall foundation poured
  • Stormwater gallery in place
  • New waterline trenching to road
  • Masonry work beginning on third floor

As of August 9, 2016, a summary of the work completed or underway.

  • Air handling equipment was craned up to mechanical penthouse
  • Water softeners installed
  • New watermain excavation underway
  • Waterproofing of new addition – West foundation wall in progress
  • Skate tile flooring removal
  • Fire sprinkler system being installed in arena

Check out our construction photo gallery at guelph.ca/vrrcrenovations