Construction crews have been busy with the following aspects of the Victoria Road Recreation Centre renovation.

Behind the scenes

As of July 18, 2016, a summary of the work completed or underway.

  • Elevator—form, place rebar and pour concrete at elevator shaft
  • Preparation for air handling units to be installed in penthouse
  • Level  and compact granular material at pool change rooms
  • Watermain replacement work underway
  • Arena sprinkler system work ongoing